November 2024 Update
1CB6DEB4-BF08-4F5C-87B1-EC9B7E628CF7
8948236B-B125-4574-B8C8-43BA36FB3E08
B3A3843D-22AE-4A35-AF97-392415EF3EB5
1CB6DEB4-BF08-4F5C-87B1-EC9B7E628CF7
1/5
• EXTERIOR GLAZING IS COMPLETE.
• DUMPSTER ENCLOSURE STEEL POST INSTALLATION IS COMPLETE.
• ROOF-TOP UNIT INSTALLATIONS ARE COMPLETE.
• UNITS B AND C MASONRY WORK IS NEARING COMPLETION.
• AREA A, FIRST AND SECOND-FLOOR TILE INSTALLATIONS ARE IN PROGRESS.
• UNIT C DRYWALL INSTALLATION IS IN PROGRESS.
• UNIT A FIRE SUPPRESSION SYSTEM INSTALLATION IS IN PROGRESS.
• UNIT B TAPE AND BED IS IN PROGRESS.