November 2024 Update

• ATHLETIC LIGHTING WORK IS COMPLETE.
• SOFTBALL FIELD GRAVEL INSTALLATION IS COMPLETE.
• SOFTBALL FIELD COMPACTION AND FINAL GRADE ARE IN PROGRESS.
• BASEBALL FIELD FINAL GRADE IS IN PROGRESS.
• DUGOUT STRUCTURAL STEEL INSTALLATION IS COMPLETE.
• BACKSTOP NETTING POLE INSTALLATION IS COMPLETE.
• ELECTRICAL UNDERGROUND INSTALLATIONS ARE IN PROGRESS.
• DUGOUT MASONRY WORK IS IN PROGRESS.