April 2025 Update

51B43BE7-58A0-474B-A707-7571445CFA0F

22E88003-CBCB-4534-BFB8-ED112A69A9FB

EE885A71-72E1-4FE8-B4E8-0328265BBFA5

51B43BE7-58A0-474B-A707-7571445CFA0F
1/6
• BASEBALL AND SOFTBALL DUGOUT WORK IS COMPLETE.
• TENNIS COURT FIBER INSTALLATIONS ARE COMPLETE.
• BASEBALL FIELD, SOFTBALL FIELD, AND PAVILION TURF INSTALLATIONS ARE COMPLETE.
• CONCESSION PLUMBING AND BATHROOM EQUIPMENT INSTALLATIONS ARE COMPLETE.
• FENCE WINDSCREEN INSTALLATIONS ARE IN PROGRESS.
• CONCESSION STAND FOOD SERVICE EQUIPMENT INSTALLATIONS ARE IN PROGRESS.
• FRONT ENTRY GATE INSTALLATIONS ARE IN PROGRESS.
• LANDSCAPING IS IN PROGRESS.