March 2025 Update

FEFF6E4B-BC91-4406-9E47-55CB61D19988

C063BF8D-C133-4C2F-855E-705961416083

68E58D69-A46C-4045-A0BE-AFBFD5F56FD8

FEFF6E4B-BC91-4406-9E47-55CB61D19988
1/5
• BASEBALL AND SOFTBALL FIELD BACKSTOP PADDING INSTALLATIONS ARE COMPLETE.
• SOFTBALL AND BASEBALL DUGOUT EQUIPMENT INSTALLATIONS ARE COMPLETE.
• FRONT ENTRANCE TURF AND LOGO INSTALLATIONS ARE COMPLETE.
• SCOREBOARD INSTALLATION IS COMPLETE.
• TICKET BOOTH CANOPY INSTALLATION IS COMPLETE.
• TICKET BOOTH SIGNAGE TRUSS INSTALLATIONS ARE IN PROGRESS.
• PAVILION TURF INSTALLATIONS ARE IN PROGRESS.
• PARKING LOT STRIPING IS IN PROGRESS.