January 2025 Update

DF26C0AD-6656-460B-8408-F6959747D821

20AF1DD2-8FF9-4D3F-98D9-28AD5DE64AC9

80745BFB-3409-4BA0-8998-4B58EE2171D8

DF26C0AD-6656-460B-8408-F6959747D821
1/5
• FRONT ENTRY GLASS AND FRAME INSTALLATIONS ARE IN PROGRESS.
• AREAS A, B, AND C TILE INSTALLATIONS ARE IN PROGRESS.
• AREAS A AND B PAINTING ARE IN PROGRESS.
• GANG AND SINGLE RESTROOM ACCESSORY INSTALLATIONS ARE IN PROGRESS.
• AREA A LOW VOLTAGE INSTALLATIONS AND WIRE PULLING ARE IN PROGRESS.
• MEDIA CENTER PAINTING AND DRYWALL INSTALLATION ARE IN PROGRESS.
• PLAYGROUND GRADING AND DIRT WORK ARE IN PROGRESS.
• PARKING LOT LIGHT INSTALLATIONS ARE IN PROGRESS.